This Week

Brenner Excavating crews placed sand and gravel for the pathway base along Kuttshill Drive. They also removed the top soil along Brewer Avenue and began prepping the existing surface for sand and gravel. They installed new drainage measures near Northedge Drive and began finalizing the grades in preparation for paving.

 

Next Week

The contractor will continue placing sand and gravel along Brewer Avenue.

Due to the volume of traffic along Kuttshill Drive and Brewer Avenue, please watch for flagpersons and additional traffic control between 2:00 and 4:00 pm while work is in progress. Please be mindful of your speed and the safety of those working.