We’re back this week with more construction progress on Southern Avenue!

 

Work Completed This Week

  • Traffic control was set up and the road was milled last Friday
  • The sanitary sewer was installed on Southern Avenue beginning at Peck Street and finishing almost to Jefferson Street.  The sewer installation at Sanford required crossing underneath an existing 16-inch diameter water main.

 

Anticipated Work Next Week

  • The remainder of the sanitary sewer will be installed up to Jefferson Street.
  • Two sanitary laterals will be installed.
  • The 6-inch water main will be deepened at Jefferson Avenue to make room for storm sewer improvements.  Water service will need to be temporarily shut down during the tie-in for some residents on Jefferson Street early next week.