Progress Update

Work on site has been focused on surface restoration including gravel base courses for paved areas and topsoil with seeding for lawn areas. Gravel base courses along the south side of Napier are complete and the site is prepared for concrete pavement construction.

 

Up Next

Concrete work for curbs, drives, and road pavement is scheduled for next week. Watermain connections on the north side of Napier at Berrien and at Downing are also planned for next week.

After the pavement construction on the south side of Napier is complete, traffic can be moved to the south side of the road. This will allow for the last stretch of watermain construction for approximately 300 feet along the north side of Napier west of Pipestone Road.