Progress Report:
The contractor installed water main through UCHS’s south drive and continued to the north towards the ending point. The last water main pipes for the year were laid, and the hydrant and valves will be installed on Monday, October 14 so testing can be done that week. Restoration south of Van Buren Street has been completed as well as most of the restoration south of UCHS’s south drive. UCHS’s south drive is being restored today and possibly tomorrow with a tentative opening on Monday.
Upcoming Work:
The restoration work will continue into next week and will tentatively be completed by Friday, October 18. The last hydrant and valve will also be installed and testing will be completed next week as well.
Extra Notes:
Although the driveway is tentatively planned to be open by Monday, October 14, it is highly advised that traffic will continue to access Unity Christian High School from the north driveway due to construction continuing to occur until October 18 from the south driveway to Van Buren Street. Testing and restoration will be wrapping up that week and it is anticipated that construction will be finished for the year by Friday, October 18 (weather dependent).
As a reminder, police officers will continue to be present to ensure safe and effective working conditions for the construction crew and stop drivers from using 48th Ave between UCHS and Van Buren Street.