Progress Report:
This week bridge crews are working on removals, including the sidewalk and decking, as well as removing the remaining column forms.
On the pathway they are continuing to work path to the east, grading, placing gravel and adding topsoil along the back side in preparation for additional paving.
Upcoming Work:
Next week work will continue on removals on the bridge. On the pathway they anticipate paving the top course on sections already based and paving the base course on an additional 2,500 feet of gravel.