Work Completed this Past Week and Recently:
- Water main in Wilson was tied in to the water system on Grand Haven Road
- All water main is now live and in service on Seng, Kunz, Aue, Petrie, Wilson and the easement between Petrie and Wilson
- Water service stubs have been installed on Wilson and Petrie
- Asphalt paving restoration has been completed for Seng, Kunz, Aue and for asphalt driveway approaches
- Gravel road restoration on Aue Road
Work Anticipated Week of October 16, 2023
- Continued water service stub installations on Wilson and Petrie
- Begin cleaning up the pavement and start remaining pavement removals on Petrie and Wilson
- Restoration along Seng, Kunz and Aue will be ongoing
- Restoration will begin along Petrie and Wilson
Work Anticipated Week of October 23, 2023
- Prepare for paving on Wilson and Petrie with gravel road base material
- Continue water service installations and begin connections of homes to new water services
Construction is scheduled to be completed in November 2023. Please watch for more information about connecting to the new water main for those residents connecting to the new water main.