Work Completed this Past Week:
- Several more important water main connections were made between the new water main and the existing water distribution system
- Water services were replaced on 7th Street and 6th Street between Broadway and Norton
- A lot of water main work was completed in Summit between 6th and 7th Street
- Water mains were connected in Oakwood at 7th Street
Work Anticipated Week of October 16, 2023
- Water Main Tie-in Is scheduled for the intersection of 6th and Summit on Tuesday, October 17, 2023
- This will affect residents on 6th Street between Broadway and Amsterdam
- A sanitary manhole will be replaced at Amsterdam and 7th Street
- Finish any remaining water service replacements
- Drainage system sewer pipe and structures will be replaced and installed at Summit and in Oakwood after the water main and sanitary sewer main work is completed
Work Anticipated Week of October 23, 2023
- Complete any remaining underground utility work
- Begin working to rebuild the roadways with grading for gravel road base and preparing for concrete curb and gutter
Roads will be repaved and reopened in mid-November 2023.