Work Completed this Past Week

  • Contractors raised the manholes to meet the final course of asphalt
  • Roughly 90% of the topsoil was installed and spread for the project

 

Work Anticipated Week of October 16, 2023

  • Continue efforts with topsoil spreading and restoration on Monday with some washout repairs after the weekend rains
  • Top course of asphalt is tentatively scheduled for Tuesday, October 17, 2023 YAY!
  • Pavement striping will go down later in the week after the top course of asphalt.
  • Continue restoration with seeding and moving mailboxes
  • Intent is to have the road full open to traffic by the end of the week next week!

 

Work Anticipated Week of October 23, 2023

  • Punchlist items
  • New street sign installations
  • Pickup and remove any remaining traffic control signs and barricades