This week, crews continued to work on the restoration efforts along Jericho Avenue. They placed the top soil and cleaned up the restoration areas and project staging areas. They also installed several hundred feet of mulch blanket to help keep the slopes stable in the upcoming rain events.
We were also able to finally resolve the remaining utility conflicts and will be able to continue with the trail construction processes as soon as possible.
With this week’s weather delays, the paving scheduled for the end of this week has been pushed to next week.