Note: Southbound US-31 on-ramp scheduled to close 10/16 with detour via Whitehall Road. See below map for details.
Work completed/in progress:
- Completed force main installation near corner of Whitehall Road and Colby Street.
- Restored Whitehall Road crossing.
- Began force main installation east of Whitehall Road toward US-31.
Anticipated work activities for the coming week:
- Continue force main installation near Peterson Road with a second crew.
- Continue force main installation east of Whitehall Road.
- Close SB US-31 on-ramp, complete open cut crossing, and restore.