Note: Southbound US-31 on-ramp scheduled to close 10/16 with detour via Whitehall Road. See below map for details.

Work completed/in progress:

  • Completed force main installation near corner of Whitehall Road and Colby Street.
  • Restored Whitehall Road crossing.
  • Began force main installation east of Whitehall Road toward US-31.

 

Anticipated work activities for the coming week:

  • Continue force main installation near Peterson Road with a second crew.
  • Continue force main installation east of Whitehall Road.
  • Close SB US-31 on-ramp, complete open cut crossing, and restore.