Work Completed this Past Week and Recently:

  • All concrete restoration is now complete with the final piece that went in this past Tuesday being the decorative concrete in the crosswalk south of the railroad tracks
  • Base course of asphalt was placed 2 weeks ago on the path
  • Manhole castings were raised to the final elevation 2 weeks ago in the roadway

 

Work Anticipated Week of October 16, 2023

  • Lighting conduit and bases will be going in

 

Work Anticipated Week of October 23, 2023

  • Final course of asphalt is tentatively planned for Monday, October 23, 2023
  • Striping will be done shortly afterwards
  • Removal of barricades and road to be re-opened to traffic before the end of the week by October 27, 2023
  • Additional work will remain for the installation of the new lighting on Glenside