This Week:

  • B&L Excavation completed the water main installation on Freska Lake Drive.
  • B&L Excavation pressure tested and disinfected the water main on Freska Lake Drive.
  • Private water service installation continued.

 

Next Week:

  • B&L Excavation will connect the new water main to the existing water main at 10 Mile Road in Freska Lake Drive.
  • Water service installation will be completed on Freska Lake Drive the first half of next week.
  • B&L Excavation will work on clean up along Freska Lake Drive and rebuild the road.
  • Paving of the road is tentatively scheduled for next Friday, October 20. This is weather dependent and may be pushed into the following week.
  • Private water service installation will continue. All water services, except for Freska Lake Drive, area available for connection. Residents may coordinate their connection with the contractor they selected.

 

Please contact any project representative if you have questions or concerns.