This Week:
- Dean’s completed the 16-inch transmission main construction along Pine Island Drive.
Next Week:
- Concrete curb and gutter will be replaced on Monday along Pine Island Drive.
- Paving is tentatively scheduled for next Thursday pending weather related delays.
- Dean’s will work on restoration along Pine Island Drive.
Please contact any project representative if you have questions or concerns.