Progress Report

Private water service installation continued throughout the project area. If you have not already contacted a prequalified general contractor to install your water service, you must do so as soon as possible to ensure that you can meet the 60-day connection requirement.

 
This week:
  • CL Trucking continued to work on restoration work throughout the project.
  • Pine Hill Drive was graded in preparation for paving.
  • Michigan Paving and Materials (CL’s asphalt subcontractor) was on site and completed most of the asphalt restoration including top course on driveways and road patches, as well as all of Pine Hill Drive.

 

Next week:
  • CL Trucking will continue to work on lawn restoration along side new asphalt and will continue to work on cleaning up the project site.
  • Tree clearing is tentatively scheduled to take place along the south end of Meek Drive south of the Hamilton Woods neighborhood.

 

November:
  • CL Trucking has indicated they will have a pipe crew back on site to complete the water main and water service installation on Meek Drive, south of Korben Woods Drive, starting November 1st.
 

Please contact a project representative if you have questions or concerns.

 

What to Expect

October

·      Lawn restoration and project clean up

November

            ·      Watermain and water service construction on Meek Drive