Progress Report

Private water service installation continued throughout the project area. If you have not already contacted a prequalified general contractor to install your water service, you must do so as soon as possible to ensure that you can meet the 60-day connection requirement.

This week:
  • Reith-Riley (Wyoming’s asphalt subcontractor) completed paving on Wildwood Creek Drive, asphalt driveways and approaches, and necessary road patches.
  • Wyoming continued to work on lawn restoration along Pixley Avenue and overall project clean up.

 

Next week:
  • Wyoming will complete final lawn restoration along the edges of all newly paved areas.
  • Wyoming will work on overall project clean up with the goal of having the project completed by the end of the week.

 

Please contact any project representative if you have questions or concerns.

 

What to Expect

October
  • Final lawn restoration and project clean up