Progress Report

This week:
  • Dean’s completed water service installation along Packer Drive up to Van Dam Drive.
  • Dean’s started to grade the lane of Packer Drive that was removed for water main construction in preparation for paving next week.
  • Dean’s continue to complete roadside restoration.
  • Concrete curb and gutters were replaced at the intersections of Las Vegas Drive, Rogue Hill Court, and Van Dam Drive.
 
Next week:
  • Paving on Packer Drive is tentatively scheduled for next Monday (10/18) and Tuesday (10/19).
  • Dean’s will continue to install water main on Van Dam Drive.

Please contact any project representative to the left if you have questions or concerns.

 

What to Expect

October
  • Water main and water service construction along Van Dam Drive
  • Water main construction along private gravel drive south of Rogue Hill Court
November
  • Water service construction along private gravel drive south of Rogue Hill Court
  • Project clean up
Spring of 2022
  • Water main and water services along Rogue Hill Court, Rogue Hollow Court, and Packer Woods Drive