Progress Report

This week:
  • Dykema completed water main installation on Butternut Drive and Bittersweet Drive.
  • The Plainfield Water Department will work with Dykema to pressure test and disinfect the newly installed water main on Brewer Avenue.
 
Next week:
  • Dykema will complete the water main installation through the private easements out to 7 Mile Road.
  • The Plainfield Water Department will work with Dykema to pressure test and disinfect the newly installed water main on Bittersweet Drive and Butternut Drive.
  • Dykema will replace the two culverts under Brewer Avenue at the connection point near the existing hydrant.
  • Dykema will work on water service installation along Brewer Avenue.

Please contact any project representative below if you have questions or concerns.

 

What to Expect

October
  • Water main and water service construction.
Late October/Early November
  • Road restoration is planned for the last week of October.
  • Driveway and lawn restoration will be completed in early November.
Spring of 2022
  • Lawn restoration will be touched up as necessary next spring to ensure good grass growth