Work completed this past week:
- Manhole #12 installed.
- Sanitary sewer installation completed.
- Sewer meter in Union Pier intersection installed.
Summary of activities expected for the remainder of the month:
- Complete electrical and integration work related to the meter.
- Acceptance testing of the sanitary sewer force main.
- Work on remaining punch list items.