Work completed this past week:

  • Manhole #12 installed.
  • Sanitary sewer installation completed.
  • Sewer meter in Union Pier intersection installed.

 

Summary of activities expected for the remainder of the month:

  • Complete electrical and integration work related to the meter.
  • Acceptance testing of the sanitary sewer force main.
  • Work on remaining punch list items.
Manhole #12 Installation