Progress Report: The Contractor finished up water main installation on Monday. Restoration occurred on Monday-Wednesday. No work occurred on site on Thursday and Friday as the Contractor waits on test results for the main.
Upcoming Work: Once the test results come back for the transmission main, the Contractor plans then on finishing up restoration in the area. The Contractor is hoping to be complete with work on site for the year and be off site before or by Friday, October 25, in which at that time the detour will be removed (weather and test result dependent).© 2025 Prein&Newhof, All Rights Reserved