Work completed the last week:
- Approximately 400 feet of force main installed.
- Air release manhole installed.
- Lakeside Road crossing completed.
- Lakeside Road to be temporarily restored and opened to traffic by tomorrow (10/3).
Summary of activities expected for next week (October 5 – 10):
- Close Red Arrow Highway between Warren Woods Road and Lakeside Road.
- Install force main across Red Arrow Highway.