Work completed the last week:

  • Approximately 400 feet of force main installed.
  • Air release manhole installed.
  • Lakeside Road crossing completed.
  • Lakeside Road to be temporarily restored and opened to traffic by tomorrow (10/3).

 

Summary of activities expected for next week (October 5 – 10):

  • Close Red Arrow Highway between Warren Woods Road and Lakeside Road.
  • Install force main across Red Arrow Highway.