Work completed the past week:

  • Approximately 50 feet of 48-inch sanitary sewer installed and air tested.
  • Manholes #10 and #11 installed.
  • Approximately 300′ of 36″ sanitary sewer installed.
  • Began grading northbound lane of Red Arrow Highway and installing aggregate base.

 

Summary of activities expected for next week (October 5 – 10):

  • Complete 36-inch sanitary sewer installation.
  • Pave first layer of asphalt on northbound lane of Red Arrow Highway.