This Week:
- B&L Excavation rebuilt portions of the road on Freska Lake Drive.
- B&L Excavation disinfected the water main again on Freska Lake Drive due to failed samples end of last week. Two passing tests were received middle of the week.
- B&L Excavation completed the final water main tie-in on Thursday.
- B&L Excavating is starting to install water service stubs today (Friday) on Freska Lake Drive.
- Private water service installation continued.
Next Week:
- B&L Excavation will complete water service stub installation on Freska Lake Drive Monday.
- B&L Excavation will work on lawn restoration along Freska Lake Drive and replace gravel on the road.
- Paving of the road is tentatively scheduled for the end of next week. This is weather dependent.
- Private water service installation will continue. Residents may coordinate their connection with the contractor they selected.
Please contact any project representative if you have questions or concerns.