This Week:

  • B&L Excavation rebuilt portions of the road on Freska Lake Drive.
  • B&L Excavation disinfected the water main again on Freska Lake Drive due to failed samples end of last week. Two passing tests were received middle of the week.
  • B&L Excavation completed the final water main tie-in on Thursday.
  • B&L Excavating is starting to install water service stubs today (Friday) on Freska Lake Drive.
  • Private water service installation continued.

 

Next Week:

  • B&L Excavation will complete water service stub installation on Freska Lake Drive Monday.
  • B&L Excavation will work on lawn restoration along Freska Lake Drive and replace gravel on the road.
  • Paving of the road is tentatively scheduled for the end of next week. This is weather dependent.
  • Private water service installation will continue. Residents may coordinate their connection with the contractor they selected.

 

Please contact any project representative if you have questions or concerns.