Work Completed this Past Week:

  • The sanitary sewer manhole was replaced at the intersection of Amsterdam and 7th Street
  • The final water main tie-ins were completed at 6th and Summit – all water main work is now complete.  The old water main in 7th Street is now out of service.
  • More water service replacements took place on 6th Street
  • Drainage system pipe and structures were replaced on 7th Street

 

Work Anticipated Week of October 23, 2023

  • Contractors will work to complete the remaining underground utility work including the last bit of drainage and storm sewer replacements at Summit and 6th Street
  • Begin building road on 7th Street and Amsterdam and Summit with road base gravel and preparations for concrete curb and gutter

 

Work Anticipated Week of October 30, 2023

  • Concrete curb and gutter is tentatively scheduled for early in the week of October 30 on 7th Street
  • Concrete driveways and sidewalk will be done
  • Grading of roadway will continue in preparation for asphalt paving

 

Roads will be repaved and reopened in mid-November 2023.