This week, crews from Brenner Excavating and Riverworks Construction continued to make progress on the remaining sections of path. As noted earlier, the pathway grading process moves quickly. The contractor is hoping to have the next section ready for paving by the end of next week!
They have installed several sections of storm sewer and began the restoration work along Whitneyville as well! Riverworks has also been working quickly and has moved onto pile driving for the next section of boardwalk along 66th Street.
Next week, as weather cooperates, the crews will continue to install storm sewer and aggregate base along McCords. They will also continue the topsoil restoration process along the previously paved areas. Boardwalk crews will push forward rain or shine to continue their great progress!