This Week:
- Concrete curb and gutter was replaced at side streets along Pine Island Drive.
- Concrete sidewalk was replaced at Pendleton Drive.
- Driveway restoration was completed along Pine Island Drive.
- Lawn restoration along Pine Island Drive was completed.
Next Week:
- Paving of side street entrances off Pine Island Drive is scheduled for Tuesday.
- Dean’s will continue final restoration work next week and make any repairs to damaged irrigation systems.
- Pine Island Drive will be restriped after the traffic control is removed along Pine Island.
Please contact any project representative if you have questions or concerns.