  • Concrete curb and gutter was replaced at side streets along Pine Island Drive.
  • Concrete sidewalk was replaced at Pendleton Drive.
  • Driveway restoration was completed along Pine Island Drive.
  • Lawn restoration along Pine Island Drive was completed.

Next Week:

  • Paving of side street entrances off Pine Island Drive is scheduled for Tuesday.
  • Dean’s will continue final restoration work next week and make any repairs to damaged irrigation systems.
  • Pine Island Drive will be restriped after the traffic control is removed along Pine Island.