This Week:
- CL Trucking located and repaired a leak in the new 12-inch water main just south of 11 Mile Road. After the leak was repaired the pressure test passed and the water main was disinfected.
- CL Trucking continued to install water services along the east side of Algoma Avenue.
- Concrete curb and gutter began to be replaced along Algoma Avenue.
Next Week:
- 12-inch water main construction along 11 Mile Road.
- 8-inch water main construction along Winding Ridge Trail may begin late next week.
- Water service installation on Algoma Avenue south and north of 11 Mile Road.
- Concrete curb and driveway replacement along Algoma Avenue.