Progress Update

Watermain installation along the south side of Napier Avenue from Grove Avenue to Dewey Avenue is mostly complete. The portion of the project has gone relatively smoothly, with some minor changes in the depth of the new watermain due to the depth of existing sewer laterals.

 

Up Next

Watermain installation at the Napier and Grove intersection will be next, including the installation of watermain to approximately 200 feet west of Grove Avenue.  Once this portion of the new watermain has been installed, the watermain installed to date will be tested and the focus will shift to Napier Avenue water services and restoration of driveways.  Once the majority of Napier avenue water service line work and restoration work is complete, the work on Dewey Avenue watermain installation will begin.