Progress Report
Private water service installation continued throughout the project area. If you have not already contacted a prequalified general contractor to install your water service, you must do so as soon as possible to ensure that you can meet the 60-day connection requirement.
This week:
- Reith-Riley (Wyoming’s asphalt subcontractor) completed paving the top course on road patches.
- Wyoming completed lawn restoration throughout the project and general project clean up.
Next week:
- Wyoming will work on removing all the temporary traffic controls and complete any final project clean up.
- Private water service installation will continue.
What to Expect/Project Timeline
October
- Final project clean up
- Private water service installation