Progress Report

Private water service installation continued throughout the project area. If you have not already contacted a prequalified general contractor to install your water service, you must do so as soon as possible to ensure that you can meet the 60-day connection requirement.

This week:
  • Reith-Riley (Wyoming’s asphalt subcontractor) completed paving the top course on road patches.
  • Wyoming completed lawn restoration throughout the project and general project clean up.
Next week:
  • Wyoming will work on removing all the temporary traffic controls and complete any final project clean up.
  • Private water service installation will continue.

 

What to Expect/Project Timeline

October
  • Final project clean up
  • Private water service installation