Progress Report

This week:
  • Black Gold (Dean’s paving subcontractor) completed asphalt restoration on Packer Drive and on asphalt driveways impacted by construction.
Next week:
  • Tree clearing will be completed along the private gravel drive south of Rogue Hill Court.
  • Dean’s will complete water main installation on Van Dam Drive.
  • Once water main installation is completed on Van Dam Drive, the new water main will be pressure tested and disinfected.
  • Dean’s will begin to install water main on the private gravel drive south of Rogue Hill Court.
  • Concrete driveway restoration will be completed.

 

What to Expect

October
  • Water main construction along Van Dam Drive
  • Water main construction along private gravel drive south of Rogue Hill Court
November
  • Water main construction along private gravel drive south of Rogue Hill Court
  • Water service construction along Van Dam Drive and private gravel drive south of Rogue Hill Court
  • Project clean up
Spring of 2022
  • Water main and water services along Rogue Hill Court, Rogue Hollow Court, and Packer Woods Drive.

 

Important Information

Once the water service stub has been installed out to the public road right-of-way in front of your house, you will receive a letter from our staff on site informing you that your water service is ready for connection. You will have sixty (60) days from the date of the letter to connect to the municipal water system. If you have not already contacted a private water service contractor about installing your free water service, you should do so as soon as possible to ensure you can meet the sixty (60) day connection requirement.

Only those houses along Packer Drive (including the two gravel drive easements south of Rogue Hill Court) and Van Dam Drive will receive a water service as part of the 2021 construction and will be required to connect to it this year. Water main and services on Rogue Hill Court, Rogue Hollow Court, and Packer Woods Drive will be constructed next year with connection required for these houses in the spring of 2022.

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.

 

Project Timeline

October
  • Water main construction and water service installation along Van Dam Drive.
Late October – Early November
  • Water main construction along private drive easement just south of Rogue Hill Court
April 2022
  • Water main construction along Packer Woods Drive
May 2022
  • Water main construction along Rogue Hollow Drive and Rogue Hill Drive