It was a big week for the crews of Brenner Excavating and their contractors. The gravel was shaped and compacted for the entire length of the project from Rogue river Drive to Kroes Street in preparation for the paving that took place on Thursday morning. Utility crews were onsite making the final adjustments while Brenner’s crews removed the existing 5 foot sidewalk and began grading the section on Kroes street for the new 10 foot concrete path.  

Next Week

Paving will continue next Tuesday. They will start again on the south end of the project and work north. Adding the second layer of asphalt to the section that was paved on Thursday. Once complete the pavers will finish paving the rest of the path where they left off this week while Brenner’s crews begin the restoration process on the south end. Concrete ADA ramps, curbs, and sidewalks will be poured next week as well.