Progress Update

Project work along the south side of Napier between Plaza Drive and Sorter Ave is substantially complete. Watermain connections and restoration on the north side of Napier at Berrien, Downing, and Leeds Ave intersections have been underway.

 

Up Next

The final stretch of the project is upon us. Pavement removal along the north side of Napier in the last 300 feet near Pipestone Road will be starting early next week. We anticipate three to four more weeks to finish the project, which includes 300 feet of watermain, water services, concrete and asphalt pavement, and restoration.