Week 4 on Southern Avenue has come and gone.  The road base has now been installed and we’re ready for concrete to begin next week!

Work Completed This Week

  • The remainder of the storm sewer installation was completed by Tuesday
  • The sand subbase was graded and compacted
  • Aggregate base was installed over the prepared sand throughout the project area

 

Anticipated Work Next Week

  • Concrete curb and gutter is scheduled to begin to be installed either Monday or Tuesday
  • Concrete sidewalks, driveways, and ADA ramps will be installed toward the end of the week
  • The gravel base may begin to be graded in preparation for paving