Progress Report

Earlier this month, the remaining houses were connected to the water system (see progress map above). In a little over six months, 5,000 feet (0.95 miles) of 8-inch diameter water main, 11 hydrants, and 18 valves were installed. Additionally, water services were connected to each of the 71 houses in the neighborhood.

Thank you to each and every one of the residents for doing their part in a very successful water supply system extension project.