____________________________________________________________________________________________

Progress Report

As of October 21, fifty-three (53) houses (93%) have now connected to the municipal water system (see project map above). Water service quotation forms have been received for all but one of the houses along Chandler and Herrington. If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so immediately. All houses are currently past the 60-day requirement for connection to the municipal water system.