________________________________________________________________________________________

Progress Report

DeSal has completed water main construction and restoration work along Imperial Pine Drive. The Kent County Road Commission is working on finishing the lawn restoration along House Street that is associated with the road improvements project.

As of October 21, thirty-two (32) houses (71%) have now connected to the municipal water system (see project map above). Water service quotation forms have been received for all but two of the houses along House Street. If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so immediately. All houses along House Street are currently past the 60-day requirement for connection to the municipal water system.