Progress Report:

Gabe’s is nearing completion of the 44-inch ream bore (last reaming pass) and plans to be complete by next Monday (28th). K&R’s subcontractor will begin fusing the 30-inch diameter HDPE pipe today (25th).

Upcoming Work:

Tentative schedule is to pull the 30-inch HDPE pipe under Macatawa River late next week, after 2.5 months of preparation and bore work. The pipe will be strung out along the west side River Hills Drive right-of-way (ROW). Once installed, the pipe will sit approximately 60-feet below the river bottom.

Traffic/Resident Access:

Please note that as 2,000-feet of 30-inch pipe will be laid out along the west side of River Hills Drive, eastbound traffic will not be permitted to enter River Hills Drive or Scotts Drive from Lakewood Boulevard for through traffic. Residents along River Hills Drive (south of Soccer Spot), should access property from the east (via Roost Avenue). See the below detour.