Progress Report:
This week Miller Bridge began installing the forms for the deck pour. Reinforcement steel is now being placed as well.
On the pathway crew are continuing east placing aggregate, grading it and preparing for paving. Earlier this week sections of the path were paved.
Upcoming Work:
Next week work will continue preparing the deck with steel and forms.
Crews will continue to work east on the pathway, placing aggregate base, paving and restoration.