This Week:
- Dean’s Excavating installed water service stubs north of Wrens Way the first half of the week.
- Dean’s continued project clean up this week.
- Paving took place for the remaining driveways and private drive approaches.
- Dean’s and the City of Rockford pressure tested and disinfected the last section of water main south of 12 Mile Road.
Next Week:
- Dean’s will install the remaining water service stubs on Monday and Tuesday.
- Dean’s will finish lawn restoration and clean up along Summit Avenue for the year.
- Depending on the weather, Dean’s plans to wrap up construction for this year by the end of next week.
Please contact any project representative if you have questions or concerns.