All water main has been installed and tested on East Street with only water services and final connections remaining. Water main has been installed on Densmore with testing and cleaning ongoing.
Work Completed This Week
- Disinfection of the water main on East Street south of McLaughlin was completed and the main was connected at McLaughlin.
- Water service installation on East Street continued and are approximately half done.
- Densmore water main was installed, and final testing has begun.
Anticipated Work Next Week
- Water service installations will continue through the first half of the week on East Street.
- Final connections of the new main on East Street at Vine will be completed near the end of the week. This will require some water service interruptions on Vine and East Street south of Vine. Notifications will be sent out once the work is scheduled.
- Disinfection and testing of the Densmore water main will be completed and connection to the system is anticipated to occur mid-week.
- Restoration of East Street may begin near the end of the week.