Work Completed this Past Week:

  • Storm drainage structures and pipes were replaced
  • 7th Street was graded and gravel road base was placed
  • Project was prepped for new concrete curb and gutter to be installed

 

Work Anticipated Week of October 30, 2023

  • String lines will be installed and concrete curb and gutter will be installed on 7th Street on Monday, October 30, 2023
  • PLEASE do remove all vehicles from your driveway if you need them.  You will NOT have access to your driveway for about 1 week.
  • Concrete sidewalk and driveway approaches will be placed
  • Remaining storm drainage structures and pipes will be replaced
  • A new hydrant will be installed at 6th and Oakwood on Wednesday, November 1, 2023
  • Grading the road and preparing for asphalt
  • Complete any remaining underground utility work

 

Work Anticipated Week of November 6, 2023

  • Continue concrete sidewalks, sidewalk ramps, driveways, miscellaneous curbs
  • Finish grading any roadways
  • Backfilling areas between the sidewalk and curb, begin lawn restorations
  • Begin asphalt paving