This Week:
  • Concrete curb work and concrete driveway work was completed along Algoma Avenue.
  • Lawn restoration along Algoma Avenue continued.
  • Water service installation along Algoma Avenue was completed. If you live on Algoma Avenue you may now schedule the work with the contractor, you selected to install your water service into your house.
  • 12-inch water main installation along 11 Mile Road began.

 

Next Week:
  • 12-inch water main installation along 11 Mile Road will be completed.
  • 8-inch water main installation along Winding Ridge Trail will begin early/middle of next week.
  • Testing of new 12-inch water main along 11 Mile Road.
  • Paving of private driveway approaches along Algoma Avenue end of next week.

 

Please contact any project representative below if you have questions or concerns.