This Week:
  • Remaining concrete curb and gutter was replaced.
  • Base course paving of Northville Drive was completed.
  • Sidewalk replacement continued along Northville Drive. There is currently a shortage of cement which is a key ingredient in the concrete mix and has forced area plants to cut production which in return has slowed down the anticipated replacement of the sidewalks.
  • Manhole covers and catch basin covers were adjusted.
  • Driveway replacement along Northville Drive
  • Restoration activities continued, the parkway areas were graded out and new topsoil was brought in.

 

Next Week:
  • Sidewalk replacement will continue.
  • Driveway replacement will be completed.
  • Final paving of the roads is scheduled for end of next week but is weather dependent.
  • Irrigation repairs, topsoil restoration, and final seeding.