Progress
Approximately 1,000 feet of sanitary sewer and 1,350 feet of watermain have been installed to date, as shown on the map above. All pipe underneath Euclid Ave north of the I-94 Business Loop has been installed. Soil and groundwater conditions continue to be favorable.
Up Next
Pressure testing and chlorinating of the watermain will be occurring next week. Euclid Ave will be reconstructed, and the gravel base will be installed in preparation for paving. Paving is scheduled for the week of November 7.