This Week:
- The rest of the paving work was completed on the project.
- Dean’s worked on final project clean up.
- Lane striping was repainted along Pine Island Drive and Buth Drive.
Remaining Work:
- Dean’s will be back on site one more time to wrap up any loose ends.
- Traffic control devices will be removed from the site.