Progress Report

This week:
  • Tree clearing was completed along the private gravel drive south of Rogue Hill Court.
  • Dean’s installed water main on Van Dam Drive.
  • Concrete driveway restoration was completed along Packer Drive.
Next week:
  • Dean’s will complete water main installation on Van Dam Drive.
  • Once water main installation is completed on Van Dam Drive, the new water main will be pressure tested and disinfected.
  • Dean’s will begin to install water main on the private gravel drive south of Rogue Hill Court.

 

What to Expect

November
  • Water main construction along private gravel drive south of Rogue Hill Court
  • Water service construction along Van Dam Drive and private gravel drive south of Rogue Hill Court
  • Project clean up
Spring of 2022
  • Water main and water services along Rogue Hill Court, Rogue Hollow Court, and Packer Woods Drive.

 

Project Timeline

Late October
  • Water main construction and water service installation along Van Dam Drive.
Late October – Early November
  • Water main construction along private drive easement just south of Rogue Hill Court.
April 2022
  • Water main construction along Packer Woods Drive
May 2022
  • Water main construction along Rogue Hollow Drive and Rogue Hill Drive