Progress Report
This week:
- Dykema completed the water main tie-in at 7 Mile Road and private utility easement.
- Dykema completed all of the water service installations in the public right-of-way.
Next week:
- The twin culverts crossing Brewer Avenue will be removed and replaced. This work is scheduled for Tuesday.
- Dykema will work on lawn restoration.
What to Expect/Project Timeline
November
- Culvert replacement across Brewer Avenue.
- Road pavement restoration.
- Driveway and lawn restoration will be completed in early November.
Spring 2022
- Lawn restoration will be touched up as necessary to ensure good grass growth.