Progress Report

Black Gold (Schippers paving subcontractor) will be paving the base course of asphalt on Wallingford Drive today (10/30). The final top course of asphalt for Biddeford Drive and Biddeford Court is scheduled for next week Tuesday (11/3). Driveway restoration on Biddeford Drive and Biddeford Court will finish up this week. Next week, Schippers will have concrete crews on Wallingford Drive working on driveway restoration.

Schippers has begun lawn restoration on Biddeford Drive and Biddeford Court. Lawn restoration for the entire project will continue through next week. Final top course paving on Wallingford Drive will take place after the majority of the lawn restoration is completed.

 

What to Expect This Week (November 2 – 7)

 

Projected Timeline

 