Progress Report:
This week Miller Bridge completed the installation of the new galvanized beams and began work installing the forms for the bridge deck expansion. On the pathway crews paved the top course of asphalt west of the bridge and began restoration of this section. East of the bridge crews are continuing work clearing, graveling and grading the pathway.
Upcoming Work:
Next week Miller Bridge will focus on the installation of the form work for the deck. They anticipate also beginning the process of removing the existing brush block sidewalk on the north side of the bridge.
Pathway crews will continue work on the trail to the east, and they hope to be able to start base course paving next week here as well.