This Week:

  • B&L Excavation continued to install water main on Freska Lake Drive.
  • B&L Excavation crossed the culvert under Freska Lake Drive earlier in the week and lost one day to rain on Thursday.
  • Clean up along Freska Pines was completed earlier this week.
  • Private water service installation continued.

 

Next Week:

  • B&L Excavation will complete water main on Freska Lake Drive early next week.
  • The new water main will be pressure tested and disinfected.
  • The new water main will be connected to the existing water main at 10 Mile Road end of next week pending passing test results.
  • B&L Excavation will begin to clean up along Freska Lake Drive.
  • Paving of the road will not take place likely until the last week of October.
  • Private water service installation will continue. All water services, except for Freska Lake Drive, area available for connection. Residents may coordinate their connection with the contractor they selected.

 

Please contact any project representative if you have questions or concerns.