Note: Whitehall Road scheduled to re-open 10/10/2023. See below post for detour details.

Work completed/in progress:

  • Approximately 550′ of force main installed within Colby Street and across Whitehall Road. Force main installed to connection valving east of Whitehall Road.
  • Emergency utility pole replacement at corner of Whitehall Road and Colby Street.

 

Anticipated work activities for the coming week:

  • Repair Whitehall Road and re-open to traffic.
  • Begin force main installation east of Whitehall Road.
  • Continue force main installation near Peterson Road.